This project for the Port Authority of NY & NJ involved the installation of enclosures around the suspension cables within the four (4) anchorage chambers (NY & NJ) of the George Washington Bridge followed by installation of a
dehumidification system within each.

Additionally, extensive structural modifications were performed together with the installation of cat walks to access the anchorage. Restoration work to deteriorated concrete surfaces was also required which involved concrete removal/replacement and the installation of a new wearing surface.

Supplemental work on the bridge involved minor structural upgrades as well as placement of new asphalt wearing surface on sections of the bridge.

 